The works of the Bioceanic Corridor - Carmelo Peralta-Loma Plata section - are already in full execution. The works are being carried out in three work fronts: Filadelfia, Loma Plata (Boquerón) and Carmelo Peralta (Alto Paraguay). It is estimated that the first 25 kilometers of work will be completed this year.

The project, which has a 38-month execution period - scheduled for completion in April 2022 - will be divided into 20 sections. This is one of the works planned to promote the development of the Paraguayan Chaco and generate more jobs.

On the other hand, next May the awarding of the works for the Costanera Sur will take place in order to start the work in December. The duration of these works will be almost 40 months, with an investment of US$ 170 million for an extension of approximately 7.5 kilometers of avenue.

The project covers an area of approximately 7.5 kilometers between the banks of the Paraguay River, the Yukyty stream, the vicinity of Cerro Lambaré and the vicinity of RI14 up to Colón Avenue.

Source: MOPC and Paraguayan Information Agency

BANNER VOUGA @4
El Poder Ejecutivo aumentó el salario mínimo legal (“SML”) en Gs. 2.899.048 lo cual representa un aumento de Gs. 100.739
BANNER VOUGA _1-100
Amendments Introduced to the Regulation on the Opening of Banks, Finance Companies, and Other Credit Institutions
BANNER VOUGA _2-100
The Central Bank of Paraguay flexibilizes the term of foreign exchange forward operations

\ Follow Us